A09 Pollution Infiltration Management (WELL v2, Q2 2025)

Concept: Air · Type: Optimization · Maximum points: 2

Intent

Minimize the introduction of pollutants into indoor air through the building envelope and at building entrances.

Summary

This WELL feature requires projects to reduce transmission of air and pollutants from outdoors to indoors through the building envelope and entrance.

Issue

Research shows that approximately 65% of outdoor air particle inhalation occurs while indoors.1 Exposure to high levels of coarse and fine particulate matter inadvertently introduced into the space can lead to respiratory irritation. It has been associated with increases in lung cancer, cardiovascular disease and mortality.2 Indoor air quality and thermal comfort can be compromised by leaks and gaps that break the building’s air barrier. These weak points are not only wasteful from an energy point of view but can also lead to conditions conducive to mold growth and to the infiltration of pests or polluted air. In addition, building users can introduce particulate matter indoors through their clothes and shoes, including harmful coliforms and Escherichia coli, among other toxins.3–5

Evidence

In addition to building envelope commissioning, there is a need for measures that minimize or prevent the introduction of potentially harmful substances into indoor spaces. An example of such interventions is the installation of entryway walk-off systems and/or entryway air seals at all main building entrances.6

Requirements

A09.1 Design Healthy Entryways — 1 point

Applies to: All Spaces.

Meet all of the following options:

Option 1: Building entry design

For any functional building entrance (not including doors to balconies or terraces), the following design features are present:

Verification: On-site Photographs, Letter of Assurance – Designer

Photographs should showcase:
1) The floor entryway system, showing it is the width of the entrance.
2) A measurement tape confirming its length.
3) The entry vestibule showing either the two typically closed doorways, revolving entrance doors and/or three typically shut doors.

Quantity: At least one photograph for each functional building entrance (maximum 5).

Option 2: Building entry maintenance

Building entryway systems are cleaned, as follows:

Verification: Policy and/or Operations Schedule

Applies to: Outdoor Sport Areas.

The following requirement is met:

Verification: On-site Photographs, Letter of Assurance – Designer

Photographs should showcase:
1) The area separating the outdoor sports field from building facilities with the adjacent field and building facility clearly visible.

Quantity: At least one photograph for each distinct area.

Interiors projects may count exterior building entrances that meet the feature requirements, even if they are outside of the project boundary.

WELL Core:

Meet these requirements in the whole building. Doors that open directly from the pedestrian network to a single tenant (in a multi-tenant project) do not need to comply​​.

A09.2 Perform Envelope Commissioning — 1 point

Applies to: All Spaces.

For projects undergoing design and construction, the following requirements are met:

Verification: Technical Document (Audited)

Commissioning report
Interiors projects may count commissioning performed on the building envelope, even if outside of the project boundary.

WELL Core:

Meet these requirements in the whole building.

Frequently asked questions

For an interiors project, could a walk-off system be provided at the tenant entrance to comply?

Yes, a walk-off system can be used at the tenant entrance to comply if the building owner has not provided one at the functional building entrances.

Can a combination of the options (e.g., mats and grilles, multiple mat sections) be utilized to achieve Part 1a?

Yes, a combination of the options under Part 1a may be used as long as they total 10 feet in length (and at least the width of the entrance).

Would maintenance/service entrances require implementing healthy entry design strategies? Can common examples of functional building entrances be provided?

If the maintenance and service entrances are designed to be used by pedestrians and unlocked during regular business hours, they would require healthy entry design strategies.
 
Common examples of functional building entrances include the main building entrance, entrances used by maintenance and service staff, as well as any building entryways designed for people attached to parking structures or underground parking garages. Atypical entrances, emergency exits, atriums, connections between concourses and interior spaces are not included.

Does the walk-off surface have to be continuous over its entire length and are any gaps in the surface allowed?

Small gaps (less than 0.3 m [1 ft]) between sections of the walk-off surface are acceptable.

References

  1. Fisk WJ. Review of some effects of climate change on indoor environmental quality and health and associated no-regrets mitigation measures. Build Environ. 2015;86(January):70-80. doi:10.1016/j.buildenv.2014.12.024
  2. Du Y, Xu X, Chu M, Guo Y, Wang J. Air particulate matter and cardiovascular disease: The epidemiological, biomedical and clinical evidence. J Thorac Dis. 2016;8(1):E8-E19. doi:10.3978/j.issn.2072-1439.2015.11.37
  3. Licina D, Tian Y, Nazaroff WW. Emission rates and the personal cloud effect associated with particle release from the perihuman environment. Indoor Air. 2017;27(4):791-802. doi:10.1111/ina.12365
  4. Lax S, Hampton-Marcell JT, Gibbons SM, et al. Forensic analysis of the microbiome of phones and shoes. Microbiome. 2015;3(1):21. doi:10.1186/s40168-015-0082-9
  5. Licina D, Nazaroff WW. Clothing as a transport vector for airborne particles: Chamber study. Indoor Air. 2018;28(3):404-414. doi:10.1111/ina.12452
  6. Younes C, Shdid CA, Bitsuamlak G. Air infiltration through building envelopes: A review. J Build Phys. 2012;35(3):267-302. doi:10.1177/1744259111423085
  7. U.S. Green Building Council. LEED BD+C: New Construction | v4 - LEED v4. 2018. https://www.usgbc.org/sites/default/files/LEED v4 BDC_07.2.18_current.pdf.
  8. Wenger Corporation. Planning your athletic facility. https://www.wengercorp.com/Construct/docs/Athletic Planning Guide by Wenger GearBoss.pdf.